Service Link Primary Data Center Buildout
Mission Critical

Service Link Primary Data Center Buildout

Pennsylvania

PROJECT OVERVIEW

Design-build contract to build-out a new 5,800 square feet of primary data center in the home office location. This project included full construction services and design services (architectural, electrical, mechanical and structural). System installation included 90 tons of air condition CRAC units, 45 tons of high density in-row cooling, FE-25 fire protection, a new dual commercial service, (2) 750 kW stand-by generator, dual 300 kVA UPS units with (4) 225 amp remote power panels (RPP) all installed in a A/B bus configuration.

PARTNERS

  • LLI Engineering

Download Project Data Sheet

Download the complete project documentation and analysis

PROJECT STATS

$3,100,000
budget
10 months
duration