Iron Mountain Edison
New Jersey
PROJECT OVERVIEW
Iron Mountains New Jersey project is a 1,000,000 sf data center facility on a 43 acre site. Multiple projects were constructed to provide additional infrastructure and update existing critical Medium Voltage services. - The addition of a 4th Systecon 1250 Modular ChillerPlant - The addition of (4) 2.5 MW Generators to provide paralleling services - Replacement of all service entrance switchgear to an active data center - Replacement of switchgear to serve critical loads
PARTNERS
- Noel Musical Group Architecture
- Arizona Pinnacle Engineering
Download Project Data Sheet
Download the complete project documentation and analysis
PROJECT STATS
$28,000,000
budget
28 months
duration