Mission Critical
Expedient Denver
Colorado
PROJECT OVERVIEW
The Owner acquired a 32,000 square foot raised floor data center, including support and office areas, located in the technology corridor of Centennial, Colorado. Etzel was responsible for the comprehensive design, engineering, and construction of a full building renovation to meet Expedient’s operational standards. The scope of work included the replacement of the existing UPS system with dual 800 kVA lithium battery systems, a complete remodel of the data center and office spaces, and general upgrades to enhance the facility’s overall appearance and functionality.
PARTNERS
- AZPE Engineers & Architects
- Donwil
- GBBN Architects
- LLI Engineering
Download Project Data Sheet
Download the complete project documentation and analysis
PROJECT STATS
$4.3 Million
budget
11 Months
duration